January Update
The level one floor slab has been poured just before Christmas – a significant milestone that brings the project further above ground. This stage has allowed the team to step onto the balconies of the townhouses and first-floor apartments for the first time, offering a real sense of the outlook across Subiaco Common and the connection to the surrounding parklands.
November Update
Progress continues at pace on site, with ground floor formwork now being assembled in preparation for the slab pour – a monumental moment for the foundation of the building.
This level will form the future entrance to Price Street – the first impression for residents and guests, setting the tone for the experience of Price Street, Subiaco
West to West continue to deliver with precision and momentum on track to pour the first-floor slab before Christmas.
October Update
A milestone week onsite, with the Basement 1 slab now poured – marking a major step forward for Price Street, Subiaco.
With the ground floor scheduled for November, Price Street will start to rise above the treetops of Subiaco Common.
September Update
Momentum continues at Price Street, with the Basement 2 slab now being poured. Next, the columns, walls and stair core will rise, bringing the structure to life.
Behind the scenes, the ADC team are working closely with West to West Builders to procure finishes — from tiles to benchtops — ensuring every residence reflects the quality and detail of Price Street.
August Update
Construction at Price Street is progressing well, with the tower crane now being installed and the first footings poured — a major milestone as the building begins to rise.
July Update
With in-ground civil and piling works now complete—and crane foundations nearing readiness—the groundwork is firmly in place for what’s to come.
February Update
Breaking ground. West to West has officially mobilised to site.